  • 16 ‘plan’ fields do not match the ‘reference’ field in the plan dataset
Reference Plan Plan event Event date Actual date Entry date Notes
Great-Yarmouth-Local-Plan-2045-plan-publish-notice-intention-commence

Great-Yarmouth-Local-Plan-2045

Missing associated entity

publish-notice-intention-commence 2026-06-30 2026-06-30 Publishing the notice of intention to commence Local Plan preparation is a new requirement. It gives communities and stakeholders advance notice of plan making and sets out when and how they can get involved. The notice must be published at least 4 months before Gateway 1.
Great-Yarmouth-Local-Plan-2045-scoping-consultation-start

Great-Yarmouth-Local-Plan-2045

Missing associated entity

scoping-consultation-start 2026-08-24 2026-07-30 This is a new requirement and seeks to ask what people would like to see in their Local Plan and how they want to be engaged in the process.
Great-Yarmouth-Local-Plan-2045-scoping-consultation-end

Great-Yarmouth-Local-Plan-2045

Missing associated entity

scoping-consultation-end 2026-10-05 2026-07-30 All comments (representations) on the scoping consultation must be received on or before this date.
Great-Yarmouth-Local-Plan-2045-call-for-sites-consultation-start

Great-Yarmouth-Local-Plan-2045

Missing associated entity

call-for-sites-consultation-start 2026-08-24 2026-07-30 An opportunity for stakeholders to submit sites for consideration in the new Local Plan. This is not a formal consultation required by legislation.
Great-Yarmouth-Local-Plan-2045-call-for-sites-consultation-end

Great-Yarmouth-Local-Plan-2045

Missing associated entity

call-for-sites-consultation-end 2026-10-05 2026-07-30 All sites must be received on or before this date.
Great-Yarmouth-Local-Plan-2045-gateway-1-self-assessment

Great-Yarmouth-Local-Plan-2045

Missing associated entity

gateway-1-self-assessment 2026-10-30 2026-06-30 This new requirement is a self assessment summary confirming that we have published the timetable and notice, completed the scoping consultation, and have a project plan in place to begin the formal stage of preparing the Local Plan. Once we complete Gateway 1, we have 30 months to prepare and adopt the plan.
Great-Yarmouth-Local-Plan-2045-content-evidence-consultation-start

Great-Yarmouth-Local-Plan-2045

Missing associated entity

plan-content-evidence-consultation-start 2027-04-01 2026-06-30 This second formal consultation sets out the proposed vision, aims and objectives, and a summary of the policy topics the plan will cover. We will also publish a summary of the evidence proposed to support the plan. This stage should will provide an opportunity to comemnt on submitted sites.
Great-Yarmouth-Local-Plan-2045-content-evidence-consultation-end

Great-Yarmouth-Local-Plan-2045

Missing associated entity

plan-content-evidence-consultation-end 2027-05-01 2026-06-30 All comments (representations) on the proposed Local Plan content and evidence consultation must be received on or before this date.
Great-Yarmouth-Local-Plan-2045-gateway-2-advice-sought

Great-Yarmouth-Local-Plan-2045

Missing associated entity

gateway-2-advice-sought 2027-09-01 2026-06-30 This new requirement is a formal method of obtaining feedback from a planning inspector on the draft plan and supporting evidence, ensuring our approach aligns with national policy, guidance and legislation.
Great-Yarmouth-Local-Plan-2045-gateway-2-advice-published

Great-Yarmouth-Local-Plan-2045

Missing associated entity

gateway-2-advice-published 2027-10-01 2026-06-30 Date of publication will depend on the duration of Gateway 2.
Great-Yarmouth-Local-Plan-2045-proposed-plan-consultation-start

Great-Yarmouth-Local-Plan-2045

Missing associated entity

proposed-plan-consultation-start 2028-04-01 2026-06-30 This 8 week consultation is on the final version of the plan and includes the proposed site allocations.
Great-Yarmouth-Local-Plan-2045-proposed-plan-consultation-end

Great-Yarmouth-Local-Plan-2045

Missing associated entity

proposed-plan-consultation-end 2028-05-01 2026-06-30 All comments (representations) on the proposed Local Plan consultation must be received on or before this date.
Great-Yarmouth-Local-Plan-2045-gateway-3-advice-sought

Great-Yarmouth-Local-Plan-2045

Missing associated entity

gateway-3-advice-sought 2028-09-01 2026-06-30 This new requirement is a final check by an external assessor to confirm the plan meets planning regulations and the tests of soundness, before formally submitting it for Examination.
Great-Yarmouth-Local-Plan-2045-gateway-3-advice-published

Great-Yarmouth-Local-Plan-2045

Missing associated entity

gateway-3-advice-published 2028-10-01 2026-06-30 Date of publication will depend on the duration of Gateway 3.
Great-Yarmouth-Local-Plan-2045-examination-submitted

Great-Yarmouth-Local-Plan-2045

Missing associated entity

examination-submitted 2028-10-01 2026-06-30 The proposed Local Plan must be submitted for an independent Examination carried out by a Planning Inspector. The Examination should last no longer than 6 months.
Great-Yarmouth-Local-Plan-2045-adopted

Great-Yarmouth-Local-Plan-2045

Missing associated entity

adopted 2029-04-01 2026-06-30 Consideration of adopting the proposed Local Plan as the development plan for the Borough

How to fix this issue

Your data is missing a plan.

The plan timetable guidance explains how to fix the issue:

plan

This is the unique reference for your overall plan. For example:

  • LP-BRX-2024
  • barnet-local-plan-2021-2036
  • hertfordshire-minerals-and-waste-plan
  • essex-minerals-plan
  • essex-waste-plan
  • county-durham-supplementary-plan

The ‘plan’ field in your plan timetable dataset must match the ‘reference’ field from your plan dataset.

This diagram shows the relationship between the plan dataset and the plan timetable dataset. The reference value from your plan dataset needs to match the plan value in your plan timetable dataset. This is so that we can match your timetable to the right plan.

How to improve Great Yarmouth Borough Council’s data

  1. Fix the errors indicated
  2. Use the check service to make sure the data meets the standard